Diverse Paths for Data Centre Fiber Connectivity


A data centre developer came to BAAC in early 2026 with a clear requirement: two physically diverse fiber paths connecting its data centres to a carrier-neutral internet exchange. Before anything was designed or ordered, we ran a feasibility study to find out what the region could actually support, and how quickly. What we found changed the plan for the better.

Illustration of two separate glowing fiber paths meeting at one point, representing diverse fiber routes

Project Borealis at a glance


Client

Data centre developer (confidential)

Scope

Dual-path diverse connectivity between data centres and a carrier-neutral internet exchange

Feasibility started

Q1 2026

Design and material procurement

Q4 2026

Scheduled delivery

Q4 2027

BAAC role

Feasibility and route validation, network design, procurement, and delivery

The Challenge

Two diverse paths, on a schedule that could not slip.


For a data centre, connectivity is not a nice-to-have. If the fiber is not there when the power and the servers are, the building sits idle. Our client needed dual-path diversity so that a single cut or outage could never take its sites offline, and it needed both paths landing at a carrier-neutral exchange so it would never be locked into one provider.

The harder question was timing. Long-haul fiber depends on permits, land access, and materials that can take many months to secure. The developer needed to know early which routes were realistic, what could delay them, and what had to be ordered before design was even finished.


What the Feasibility Study Found

Four findings that shaped the project before a single conduit went in the ground.


Feasibility is where we earn our keep. By validating routes, suppliers, and approvals up front, we turned unknowns into decisions the client could act on.


A regional shortage of lit capacity

We found that carriers in the region had limited lit wavelength services available. Relying on leased capacity alone would have left the developer exposed on both availability and timing. That finding made a strong case for dedicated dark fiber.


The fastest permitting routes

Not every route moves through approvals at the same speed. We identified the paths with the quickest permitting outlook so early connections could come online sooner, without waiting on the slowest approval in the chain.


Early fiber procurement

Fiber and materials lead times can quietly set a project's real schedule. We established procurement needs early so orders could be placed in step with design, keeping the Q4 2027 delivery date protected.


Existing infrastructure, put back to work

We located existing infrastructure along the corridor that could be repurposed, and secured it for the project. Using what is already in place means less new construction and a faster path to connectivity.


Where the Project Stands

From feasibility to delivery in under two years.


Project Borealis is now moving from study into build. Here is how the work lines up against BAAC's six-stage process.


  1. Q1 2026, Feasibility and Route Validation. Routes, suppliers, permitting paths, and reusable infrastructure assessed.

  2. Q4 2026, Network and Site Design, plus material procurement. Design underway, with fiber ordered early to hold the schedule.

  3. Q4 2027, Construction and Commissioning. Scheduled delivery of both diverse paths.


Because the hard questions were answered first, design and procurement can run side by side rather than one after the other.


Why It Matters

Fiber comes before megawatts.


Data centre timelines are often set by power, but they are won or lost on connectivity. Project Borealis shows what happens when fiber is planned at the start instead of at the end: shortages are spotted early, the fastest approvals are chosen on purpose, materials are secured before they become a bottleneck, and existing assets shorten the build.